SN CLIENT PROJECTS DURATION JOB DESRIPTION ACTIVITY
1 SIEMENS LTD-DGEN Packaged Mechanical Construction of WTP Plant 12 MONHTS Packaged Mechanical Construction include all piping & structure fabrication & erection , equipment erection etc UGD,UGJ & UPQ Building Plant Piping & Equipment Erection & Alignment
2 SIEMENS LTD-UNOSUGEN Packaged Mechanical Construction of WTP Plant 8 MONHTS Packaged Mechanical Construction include all piping & structure fabrication & erection , equipment erection etc UGJ Building
3 SIEMENS LTD-DGEN Commissioning Manpower Assistance 12 MONTHS Manpower Assistance to Commissioning Team – all three units Turbine Trial Run, Punch Point Related Work , Flushing Work etc
4 SIEMENS LTD-UNOSUGEN GT Noise Enclosure Structure 6 MONTHS Steel Structure Erection & Fabrication Smoke Test carried out
5 SIEMENS LTD-UNOSUGEN Commissioning Manpower Assistance 8 MONTHS Manpower Assistance to Commissioning Team Turbine Trial Run, Punch Point Related Work , Flushing Work etc
6 SIEMENS LTD-DGEN Frame Contact 12 MONTHS Attending LOP’s work at Dgen Site -