Successful Execution at NAYARA Vadinar Refinery Turnaround 2026

Nayara Energy

Milestone Achievement: Turnkey Execution at Nayara Energy Refinery Turnaround (TA-2026)

Date: May 2026

Vrishal Engineering Pvt. Ltd., together with its group firm Vishal Enterprise, is proud to announce the successful completion of our turnkey scope in the 2026 Turnaround (TA-2026) at Nayara Energy’s Vadinar Refinery, Jamnagar (India’s second-largest single-site refinery).

Our scope covered the turnkey Maintenance & Inspection (M&I) work of CDU-1 and the hot & cold work package of the VGO-DHDT unit, executed during the turnaround window of April – May 2026, with an executed value of USD 5.44 Mn.

Key Highlights of Our Work On-Ground:

  • Peak Deployment: Mobilised a peak site workforce of ~2,700 personnel, including 65 qualified welders (38 CS, 17 AS/SS and 10 IBR), supported by 20 torque tightening & tensioning machines.
  • Major Equipment Handled: 38 heat exchangers, 35 vessels, 34 air-fin coolers, 12 columns and 5 heaters, along with 311 control valves, 295 isolation valves and 203 PSV / PVRV.
  • Critical Jobs & Lifts: Replacement of the 110-inch VDU transfer line and 3 × 3 m duct (143 m) in CDU, 54 critical hydro-test loops (28,000 inch-m), 25,000 inch-dia of hot work and 2.1 lakh m³ of scaffolding.
  • Ahead of Plan: All units completed their mechanical window ahead of the planned schedule – CDU in 21 days (planned 23), VGO in 27 days (planned 28) and DHDT in 22 days (planned 23).
  • Quality & Compliance: Work executed by IBR-qualified welders under our Special Class IBR approval and ISO 9001, ISO 14001 & ISO 45001 certified management systems.
  • What it means for our clients: This execution demonstrates our capacity to mobilise large resources rapidly, manage multiple critical work fronts in parallel and deliver complex refinery turnarounds safely, with quality, and ahead of schedule.
“The VE team displayed excellent dedication, professionalism, and technical capability throughout the execution… ensured timely completion of the work as per schedule while maintaining the high standard of Safety & Quality.” — Satisfactory Performance Letter, Nayara Energy Limited