A portfolio of complex industrial execution across multiple disciplines
Recently Executed Projects
2025
Project
HH2700
Client Name
GFCL EV Products Limited
Owner
GFCL EV Products Limited
Structure
100MT
Piping
10000INM
Key Achievement
850 MT of structural steel and 53,500 inch-metre of process piping executed to a high-purity specification, achieving an internal surface finish of Ra 0.8 µm.
• Dedicated clean-fabrication facilities, qualified welding procedures and stage-wise inspection maintained throughout. • Stringent cleanliness and surface-finish requirements of the process met in full.
2025
Project
Coral 2, OSBL
Client Name
Aarti Industries Limited, Jhagadia
Owner
Aarti Industries Limited, Jhagadia
Structure
100MT
Piping
10000INM
Key Achievement
750 MT of structural steel installed within 85 days. Pipe-rack bridges were fabricated and assembled in the shop and moved to site in fully assembled condition as single modules of 18.0 m × 6.5 m × 4.0 m, eliminating piece-by-piece site assembly, compressing the erection window and substantially reducing work-at-height exposure.
2024
Project
HGU Project
Client Name
Linde Engineering Pvt Ltd
Owner
IOCL, Panipat
Structure
100MT
Equipment
100Nos
Piping
100INM
Key Achievement
280 MT of structure, 60 equipment items and 25,000 inch-metre of piping completed to a compressed programme.
Where upstream spool availability constrained the work front, the schedule was recovered by mobilising additional resources, re-sequencing work fronts and monitoring progress daily.
On the strength of this performance, the client entrusted VEPL with substantial additional scope during execution.
2024
Project
Lime Kiln Conveyer structure
Client Name
TATA Chemicals Limited
Owner
TATA Chemicals Limited
Structure
100MT
Key Achievement
1,560 MT of conveyor structure delivered and erected in fully assembled condition, covering both straight (2D) and complex 3D geometry, with erection carried out up to 65 m height.
Modularisation adopted end-to-end: bridges, transfer towers and trestles were fabricated, assembled and painted in the shop rather than built piece-by-piece at site.
Each conveyor bridge shipped as a single assembled module of 21 m × 6.8 m × 2.8 m weighing 36 MT, moved 750 km from Dahej to Mithapur as an ODC consignment.
Each module set in final position in a single crane lift, with no site piece-assembly required.
2023
Project
MPP13, MPP12, HFPO
Client Name
PI Industries Limited
Owner
PI Industries Limited
Structure
1000MT
Equipment
100
Piping
10000INM
Key Achievement
Single-point execution of 4,000 MT of structure, 1,500 equipment items and 175,000 inch-metre of piping.
Scope covered steel supply, detailed engineering, fabrication, surface preparation and painting, transportation and installation of structure.
Equipment installation and complete piping fabrication and installation.
Engineering and construction were run concurrently against a progressively released and evolving design. Continuous interface management, rolling re-planning and close coordination kept execution moving without loss of work front.
2022
Project
20131B La Porte HyCo 4
Client Name
ITT Engineering India Pvt Ltd
Owner
Air Product, USA
Structure
10MT
Piping
10000IND
Key Achievement
Export-standard fired-heater module fabrication for a US end user.
Structural steel procured to Grade E350 Gr. C (27 J at –20 °C) with EN 10204 Type 3.2 certification.
Inconel 800H coil fabrication with air solution annealing at a controlled cooling rate of 568 °C/hr.
Radiant sections modularised complete with coil installation.
All convection modules trial-assembled, including refractory installation and dry-out.
Completed modules and assemblies packed to export grade for overseas shipment.
2022
Project
IRPC Reformer fabrication
Client Name
Linde Engineering Pvt Ltd
Owner
IRPC, Thailand
Structure
10MT
Key Achievement
108 MT stack, 60 m long × 3.5 m diameter and built in three sections, together with 100 MT of ducting, supplied, fabricated, assembled, surface-prepared, painted and packed within a 10-week delivery window for an overseas reformer package.
2021
Project
Manufacturing & supply of burner piping, convection structure for GPUFP project
Client Name
Furnace Engineering INC., Japan
Owner
Bangladesh Chemical Industries Corporation, Bangladesh
Structure
10MT
Piping
10IND
Key Achievement
Manufacture and export supply of 8,930 inch-dia of burner piping and 28 MT of convection structure for a fired-heater package, executed to a Japanese engineering client’s specification and documentation requirements and shipped for installation in Bangladesh.
2020
Project
MR-205
Client Name
United Phosphorus Limited, Jhagadia
Owner
United Phosphorus Limited, Jhagadia
Structure
10MT
Equipment
10MT
Equipment
1000Inch Meter
Key Achievement
1,200 MT of structure, 560 MT of equipment and 40,000 inch-metre of piping executed as a single integrated mechanical scope, and handed over ahead of the contractual completion date.
2020
Project
B192-5A Deck for Cluster 8 Project
Client Name
L&T Hydrocarbon Engineering Limited, Hazira
Owner
L&T Hydrocarbon Engineering Limited, Hazira
Structure
10MT
Equipment
10MT
Piping
1000Inch Dia
Key Achievement
1,700 MT of structure, 124 MT of equipment and 4,000 inch-dia of piping executed as a single integrated mechanical scope, and handed over ahead of 30 days the contractual completion date.