Shutdown and turnaround execution for India’s leading refineries and petrochemical complexes
Successful execution of the main service contract for TA works at CDU III and VGO-DHDT, including replacement of the 2800 mm OD, 25 mm thick VDU transfer line and 143 m of 3 × 3 m duct, with 2,700+ manpower mobilized.
• 38 exchangers, 35 vessels, 34 air-fin coolers, 12 columns and 5 heaters handled in a single turnaround.
• 311 control valves, 295 isolation valves and 203 PSV / PVRV overhauled.
• All units completed ahead of plan: CDU in 21 days (planned 23), VGO in 27 days (planned 28) and DHDT in 22 days (planned 23).
Turnaround completed ahead of schedule.
• Turnkey static maintenance of the Sulphur Block: SRU-1 & 2, SWS-1 & 2 and ARU.
• All five units handed over early, with up to 7 days saved on SWS-2.
• Zero incident throughout execution.
• Performance bonus awarded by the client for early completion.
Complete radiant coil replacement in 7 cracking furnaces at the DFCU plant, with 16 coil sets dismantled and erected and 384 tube weld joints (2″ & 3″) per furnace on Inconel (25Cr-35Ni micro-alloy) coils.
• Zero weld repairs and zero incident across all furnaces.
• Scope also covered coil-group re-coiling, convection tubes, return bends & elbows and PQE / TLE gas inlet nozzle replacement.
• Executed under a rate contract from October 2023 to September 2025 and completed on schedule.
Complete radiant coil replacement in 7 cracking furnaces at the DFCU plant, with 16 coil sets dismantled and erected and 384 tube weld joints (2″ & 3″) per furnace on Inconel (25Cr-35Ni micro-alloy) coils.
• Zero weld repairs and zero incident across all furnaces.
• Scope also covered coil-group re-coiling, convection tubes, return bends & elbows and PQE / TLE gas inlet nozzle replacement.
• Executed under a rate contract from October 2023 to September 2025 and completed on schedule.
Awarded the main service contract for TA-26 of the NIU-NLU units (MS Block) at HPCL Visakh Refinery, executed alongside the FCC-NHT turnaround.
• Combined scope across both TA-26 packages: 35 exchangers, 20 air-fin coolers, 31 vessels / filters and 6 columns.
• About 470 isolation valves, 117 control valves, 75 PSVs and 173 hydrotest loops.
• Around 1,000 personnel planned at peak deployment across both units.